They need a total of 3 man * 3 hours = 9 man hours to finish the job
at 2.55 they have completed ( 1 + 55/60) * 3 = 5.75 man hours 3.25 more to go
now there are two working for 5 /60 hour = 1/6 man hour 3 1/12 to go
at 3:00 it will take Larry 3 1/12 hour to finish = 6:05 pm